Electrical supply survey before buying a bottling machine for a UK site

Use a Great Britain purchase-stage worksheet to confirm machine electrical data, site supply, interfaces and responsibility before collection.

Italiano

Before ordering a used filler, label applicator or case packer for a site in Great Britain, have your electrical contractor compare the installed machine with the supply available at its proposed location. This is a purchase-stage survey. It gives the supplier enough detail to quote the right work and gives your team a list of open questions before the machine is collected.

Collect the evidence from both sides

Ask the seller for a legible photograph of each electrical plate, the serial number, the electrical drawings and the list of equipment included. A complete machine and its separately supplied conveyor or cabinet can have different supply requirements. Ask the seller to identify modifications that are visible on the equipment and supply current documents where available.

Give your contractor the intended position, the site drawings and the available point of connection. Ask them to identify the applicable electrical work and verification for your project. The Health and Safety Executive provides guidance for work on electrical equipment and for equipment supplied second hand. Use your competent site team to set the safe scope of any survey, tests and installation. HSE electrical work guidance · HSE second-hand equipment guidance

Electrical purchase-survey worksheet

Assign one named person and one evidence reference to each decision.
VerificationEvidence to collectOwner and decision
Machine identitySerial numbers, cabinet labels and drawing revision for each unit suppliedSeller / ___
Supply at the machineNameplate voltage, phases, frequency and stated load for each separately fed moduleSeller and contractor / ___
Supply at the destinationContractor’s assessment of circuit provision and point of connection at the proposed locationSite contractor / ___
InterfacesDocumented boundary with existing controls, stopping arrangements and equipment along the lineIntegrator and site team / ___
Changes and verificationWork in the quote, revised drawings, test responsibility and evidence required before handoverPurchaser and integrator / ___

Translate outstanding items into the purchase order

Separate work included by the seller, work priced by the installer and information still due. For example, a quotation may cover the filler and exclude the conveyor cabinet that is shown in a demonstration. Mark the cabinet as an open item until the supplier identifies its serial number, drawings and commercial scope. Give unresolved items an owner and a decision date before booking collection. Great Britain machinery delivery scope guide

Ask about used machines for your site

Tie the cabinet and connection-point records to the removal plan before collection. The machinery dismantling and relocation guide covers what to document while the machine is still assembled.

Send the intended site in Great Britain, machine type, required production rate and any machine references you already have. Include your contractor’s open questions when requesting a quotation. Contact Used Bottling Machines UK